The May 18th
Seattle Times Traffic Lab article “Report: Time running out to salvage West
Seattle Bridge” details how the bridge must be shored up to keep from
collapsing under its own weight.
Clearly the bridge cantilever design was flawed from the beginning, whether
from lack of depth at the mid-span to support its 590 ft length, lack of
adequate post tensioning steel, or segmented construction. (A retired Boeing propulsion engineer
“suggested” solution could be a temporary mid-span support from below with
long term plans for support from above with suspension cables from towers added
to piers.)
However,
the WSDOT oversight of the West Seattle Bridge is far from their first bridge failure. First there was the Tacoma Narrows Suspension Bridge. It opened to traffic on July 1, 1940 and collapsed into Puget Sound on November 7 the same year. The original I-90 Floating Bridge sank in 1990
as had the Hood Cannel bridge eleven years earlier. The original ST 520 Bridge was structurally deficient. Its replacement endured
costly delays due to design and construction problems and opened a year and a
half late.
East Link was the
first attempt to install light rail on a floating bridge. The WSDOT used flat bed trucks to simulate
light rail cars on I-90 Bridge to conclude “the test confirmed previous findings
that the bridge can be structurally retrofitted to carry the loads associated
with the light rail system under consideration, in addition to general traffic
on the roadway”.
It took an FHWA and
legislature funded Joint Transportation Committee to convince WSDOT more
testing was needed. It remains to
be seen how long the interface between the fixed and floating parts of the
bridge can withstand the loads from four heavily loaded light rail cars.
The WSDOT problems go beyond bridge design and construction oversight to an apparent failure to understand transit basics. Transit capacity is defined by the
number of vehicles per hour times the number of potential riders in each
vehicle. The PSRC concluded in 2004 the Downtown
Seattle Transit Tunnel (DSTT) limited light rail to 60 light rail cars per hour
and that each 74-seat car could accommodate 148 riders or 8880 riders per
hour.
Yet the WSDOT agreed
to Sound Transit splitting that limited capacity between Central Link south and
East Link leaving neither with adequate transit capacity for future growth. Even more egregious they allowed Sound
Transit to confiscate the I-90 Bridge center roadway precluding two-way BRT
with 10 times light rail capacity at 1/10th the cost, 10 years
sooner.
The WSDOT response to the Freeman litigation objecting to bridge confiscation convinced a federal judge the I-90 Bridge center roadway wasn’t needed for
vehicles and thus could be used for light rail. They simply ignored a 2004 FHWA study conclusion that, even with the 4th lanes added to outer roadways, the center
roadway was needed for vehicles. Increased I-90 Bridge
congestion since center roadway closure validates FHWA concerns.
They’ve abetted Sound Transit
plans to use East Link to replace cross-lake buses rather than add transit
capacity. Apparently not realizing
bridge congestion was not due to too many buses. Sound Transit “bus intercept” agreement with Mercer Island
requires they and King County Metro halve current I-90 corridor vehicles, halving capacity. East Link operation in 2023 will
demonstrate the WSDOT abetted spending billions on a transportation system that
increases congestion along the entire I-90 corridor into Seattle.
The WSDOT approach to
I-405 congestion shows a failure to understand basics of lane capacity. A lane’s maximum vehicle capacity is
obtained by limiting traffic to 2000 vehicles per hour (vpr), assuring 45 mph. HOT lanes improve HOV velocities
by raising fees to reduce the number of vehicles from carpoolers to what’s
needed to limit traffic to the 2000 vph.
The WSDOT decision to
impose HOT on two I-405 lanes is based on their “unique” assumption HOT fees
increase lane capacity. The slower
HOT lanes with the 2nd HOT lane along Lynnwood-to-Bellevue route have
already debunked the assumption.
The problem being, during much of the commute, the 2nd HOT
lane increased GP congestion on remaining lanes, attracting more than 2000
vehicles willing to pay the WSDOT fees on the two lanes. The result being GP lanes have slowed
and HOV lanes have failed to achieve 45 mph for those paying for HOT. Future growth will add to both problems.
In 2017 the WSDOT
announced plans to begin adding 4th lanes between Renton and
Bellevue in 2019, again imposing HOT fees on 4th lanes as well as on
existing HOV lane. One can only
hope the delay is due to their belated recognition that HOT should be limited
to one lane with fees raised to limit traffic to 2000 vph
and use additional lane for GP traffic.
Again one can hope they’ll do the same to I-405 between Bothell and
Bellevue.
The bottom line is the
WSDOT history of failing to effectively oversee the design and construction of
the area’s bridges has cost the area.
However those problems will eventually be resolved. Far more damaging is their slavish support for Sound Transit Prop 1 extensions. WSDOT abetting of Sound Transit refusal to add bus transit capacity shows their failure to understand the basics of public transit. That I-405 congestion will
continue to increase on both GP and HOV lanes until WSDOT limits HOT to one
lane.
No comments:
Post a Comment