On January 25th the U.S
Department of Transportation, Federal Transit Administration and others filed
their final response to the Building a Better Bellevue’s suit action concerning
alleged environmental violations.
Like the Freeman v WSDOT/ST (See 1/25/13 post), this seems like an easy
case to win.
For example, the below paragraph from
page 2 of 14:
As applied to this case, where the
planning efforts of state and local transportation officials have come to focus
on the problem of extending the light rail system to serve a particular
corridor, it makes little sense in an environmental analysis to study the
environmental impacts of the bus-based options which plaintiffs say federal
defendants should have also evaluated.
In essence the defendants are saying
there was no need to evaluate “bus options” if Sound Transits “focus” is on the
problem of extending light rail”.
Even ST didn’t believe that since they spent 30 years evaluating various
cross-lake configurations to select the “no build” options in the DEIS and
FEIS documents.
The fact ST never seriously considered
the BRT (i.e. two-way, bus-only service on center roadway) “bus option” with its far greater capacity and accessibility at far
less cost shows a lack of competence. (See 12/7/12 post for details) ST confiscation of the center roadway for light rail will increase cross-lake congestion not decrease it. (See 8/08/12 Post)
The defendants’ response concerning the
“tunnel alternative” was to admit ST didn’t consider that option.
The notion of tunneling was raised only during
scoping and rejected at that nascent stage in the process. It was never pursued
thereafter in any serious fashion by any party.
However,
it’s significant that the “Tunnel Alternative” was the only Segment 5
configuration that didn’t violate federal environmental law by intruding on the
Mercer Slough Park when it was rejected.
It wasn’t until August 2005 that the regulation was changed from
precluding such actions unless there were “no feasible and prudent alternatives
to the use of land” to "such actions result in a de minimis impact”.
Its not clear whether the court can disagree with the defendants
apparent decision the Mercer Slough Park impairment or the devastation to the
plaintiffs’ neighborhood is de minimis .
The
defendants also make a major point of the failure of the plaintiffs to pursue
the tunnel alternative earlier.
For example from Page 5 of 14;
At no time did plaintiffs, or any other
party, comment that a tunnel alternative in Segment B was a feasible and reasonable
alternative for the South Bellevue segment that should have been evaluated in
the FEIS. Therefore, plaintiffs’ objection
to the adequacy of the FEIS on that ground has been waived.
However
during the period the Defendants claim the plaintiffs should have argued for the
“Tunnel Alternative” ST was demanding Bellevue pay an additional $200 million
if they wanted a tunnel rather than a street level train route through the city
center. Any attempt to
request a tunnel for the much longer route in Segment B would presumably result
in ST demanding substantial additional funds.
Therefore, the plaintiffs instead attempted to convince the Bellevue City Council and ST
to use the B7 alternative. This
route would have eliminated their neighborhood concerns and substantially reduced Mercer Slough impairment. It was
only after these attempts had been rejected did they initiate their current
action to protect their neighborhood, as well as Mercer Slough Park, with the “tunnel alternative” or BRT on
the I-90 center roadway.
The
question for the court would seem to be “Did the delay in raising the “Tunnel
Alternative” issue cause ST any material harm?” The fact ST recently committed to tunnel the far longer
distance from the University Station to Northgate without requiring any
surcharge would seem to negate any claims they “suffered” from the delay or
that the “tunnel alternative” resulted in substantial additional costs. (Or for
any of the other reasons ST originally rejected this option in the East
Link “scoping”.)
Again, to this retired engineer this seems like an easy case to win.
Again, to this retired engineer this seems like an easy case to win.
No comments:
Post a Comment