The Sound Transit
approach to I-90 cross-lake transit typifies their incompetence in dealing with
the area’s transportation crisis. Fifteen
years ago they could have added a 4th lane to each I-90 Bridge outer
roadway. It would have benefited commuters from both sides of the lake but particularly
“reverse” commuters.
They could have also
moved non-transit HOV to the outer roadway 4th lanes and initiated
two-way Bus Rapid Transit (BRT) on center roadway capable of more than 1000
buses an hour. Each east side
P&R could have had direct bus service to dedicated drop off and pick up
points along 4th and 2nd Aves. Thousands of commuters would have been able to leave their
cars near where they live rather than where they work, reducing congestion
throughout east side.
Instead, ST still
hasn’t added the 4th lanes and never considered two-way bus routes
on I-90 center roadway as the “no-build” option in the 2008 DEIS. Their claim East Link would provide up
to 12,000 riders per hour in each direction was shear fantasy. They recently conceded East Link will provide, at best, the
equivalent of one 74-seat car every two minutes.
They told a judge the
4th lane when (finally) added to I-90 Bridge outer roadway would
enable it to accommodate all cross-lake vehicles. They knew (or should have
known) allowing car pools on bus lanes dramatically reduces capacity. This may be why they’re planning to
force all cross lake bus riders to transfer to light rail at South Bellevue or
Mercer Island stations.
It’s bad enough
thousands of bus riders will be forced to go through the hassle of transferring
to and from light rail trains as part of their morning and afternoon commute. It’s even worse East Link won’t have nearly
the capacity needed to accommodate them.
Perhaps the most
egregious example of ST incompetence is their failure to appreciate the
problems of installing light rail on a “floating bridge”. They were the first attempt to do so with the primary problem
being assuring the “expansion joints” connecting the floating and fixed portions of the
bridge could withstand the loads from light rail trains.
ST initially recognized the problem and had the WSDOT attempt to demonstrate the
I-90 Bridge could withstand the loads using flat bed trucks to simulate light
rail cars in Sept 2005. The WSDOT
concluded “results of the test confirmed previous findings that the bridge can
be structurally retrofitted to carry the loads associated with the light rail
system under consideration, in addition to general traffic on the roadway”.
Apparently the
Washington Sate Legislature Joint Transportation Committee (JTC) was not
satisfied with WSDOT tests because they commissioned an independent review team
(IRT) to evaluate the bridge design with light rail. The results of the
IRT evaluation were documented in the “I-90 Homer Hadley Floating Bridge
Independent Review Team Light Rail Train Impacts, Final Report, Sept
2008”. It includes the following “Conclusion”:
Based on extensive study, analysis, and discussions with Sound
Transit and WSDOT the IRT has concluded that all issues associated with the
installation of LRT on the Homer Hadley floating Bridge and approach spans can
be addressed or mitigated providing that the IRT resolutions and recommendation
are incorporated.
However, several issues could affect project cost estimates and
schedules and therefore should be resolved at the earliest states of the
project design. One issue deals with a required design element (LRT
Expansion Joint Tract Bridge) has no history of use on floating bridges, and
therefore requires careful study and testing in the early stages of the
project.
Since many of the issues require additional study, analysis, and
design the IRT recommends that an independent review or peer review panel be
organized to provide oversight throughout the LRT East Link design process.
Three months later
the ST Dec 2008 DEIS included the following statement regarding floating bridge/light
rail compatibility
The
Washington State Legislature Joint Transportation Committee commissioned an
independent review team (IRT) to evaluate the bridge design with light rail.
The IRT concluded that all issues identified as potentially affecting feasibility
can be addressed.
The ST DEIS simply
ignored the “However” portion of the IRT report. The U.S. Department of
Transportation Federal Highway Administration had similar concerns. Paragraph 5
of a February 25, 2009 letter, HRW-WA/WA624 responding to Sound Transits 2008
DEIS for the East Link Project included the following:
“We do not
agree that there has been enough work done to justify the conclusion that it is
feasible to design a light rail track system to accommodate the movements of
the I-90 floating bridge” and “there is additional work to be done to determine
if it is feasible to design an expansion joint to accommodate light rail”.
One would have
thought the ST would quickly respond to IRT and FHWA concerns. Instead more than two-years later, and
having done no additional testing, ST 2011 FEIS included the same confident response
as the 2008 DEIS.
Finally, five years
after the IRT recommended “careful study and testing in the early stages of the
project”, ST decided to demonstrate their “expansion joint design” at the
Transportation Technology Center in Pueblo, Colo. The tests, conducted
during the summer and fall of 2013, were initially reported to be a success with claims
their design passed with “flying colors”.
It wasn’t until the
Jan 16th 2015
meeting with Bellevue City Council ST admitted they had not yet completed the
I-90 Bridge design. They followed that with a Feb 9th admission they hadn’t
even completed a risk assessment. Presumably
the ST failure to provide the promised “completed risk assessment" prompted a BCC April 4th
comment suggesting there may not be light rail across the I-90 bridge.
Again it’s not
clear what the caused the “problem”.
One potential reason may be the fact that, typical of ST, they chose to
do the Pueblo testing with two-car trains rather than the four they’re current
proposing for East Link. Another
may be concern the Pueblo testing didn’t adequately simulate the floating
bridge motion. Whatever the
reason the fact ST, as of the Feb 9th meeting, still didn’t have an
acceptable bridge design nearly 10 years after recognizing the problem, sets a
new standard for incompetence.
Even if they do
manage to develop an acceptable bridge design, East Link will never have the
capacity needed to meet cross-lake demands. With East Link, “never” having an acceptable bridge design
is far better than being “late”. The
“never” result is they’ll have wasted nearly a billion dollars on a light rail
system that won’t be built. (The 5/20/15 post details the utter stupidity of East Link without the "Link") “Late”
means they will be allowed to continue spending additional billions on a light
rail system that will devastate the route into Bellevue, gridlock traffic on
the I-90 Bridge, and create financial black hole for the entire area’s
transportation funding.
In conclusion, ST needs to recognize the only way to meet cross-lake commuting demand is to divide the I-90 center roadway into inbound and outbound bus-only lanes. It's something they could do in 6 months and a few million rather than the 6-7 years spending billions installing light rail tracks. Failure to do so should rate high on anybody's list of
debacles.
No comments:
Post a Comment