I presented
the following to the AWB representatives yesterday at their candidate interview
forum. They were very attentive
though it’s unclear what action they will take as a result.
Why I’m a
Candidate
I’m here
today not to ask for support for my candidacy but to ask for help exposing concerns
about Sound Transit’s East Link light rail program. In 2017 ST is going to close down the center roadway and
begin light rail construction.
Closing the center roadway will significantly increase vehicle
congestion on the bridge outer roadways.
The construction efforts will disrupt the lives of those along the route
into Bellevue and the downtown Bellevue area for 6-7 years.
When light
rail begins operation, 20,000 transit riders will be forced to transfer each
morning and afternoon to and from light rail trains at either South Bellevue or
Mercer Island. East Link won’t
have the needed capacity to meet peak commute demand. As a result I-90 corridor commuters during the peak commute
will have to choose between trying to drive into Seattle on a heavily congested
outer roadway or ride a bus to a light rail station and attempt to get on an
overcrowded light rail car.
Not only
will cross-lake commuters suffer, light rail operating expenses will dwarf
potential fare box revenue. ST
will be forced to subsidize East Link by $285 million annually to make up for
the short fall.
The
clearest example of ST problems is there schedule for adding 4th
lanes to the I-90 Bridge outer roadways. The added lanes have been part of any proposed
cross-lake improvement since the mid ’90’s. The cost would have been minimal
and cross-lake commuters from both sides of the lake would have benefitted,
particularly those going in the reverse commute direction. By the time ST finally adds the lanes in
2017 thousands of commuters will have needlessly faced more than 20 years of
increased congestion.
Why the
delay for something so inexpensive and yet so beneficial? My guess is ST had two reasons. The first was they were concerned about being “forced” to
consider moving the non-transit HOV traffic to the 4th lanes and
dividing the center roadway into inbound and outbound bus rapid transit (BRT)
lanes. It’s difficult to believe
ST never considered BRT during the years spent studying ways to improve
cross-lake commuting.
It could
have been initiated some 15 years ago for a tiny fraction of light rail
cost. It had 10 times light rail
capacity that could have provided every eastside P&R with express bus
routes directly into designated drop off points in Seattle. The improved service would have attracted
more transit commuters reducing congestion throughout east side. ST was “concerned” they’d never be
allowed to shutdown BRT for light rail and consequently never “considered” it
as the “no-build” alternative in the DEIS.
Instead
they sold East Link with DEIS claims it could accommodate up to 12,000 riders per
hour (RPH) in each direction and increase I-90 transit capacity by 60%. However, East Link operating schedules
call for a maximum of one 4-car train every 8 minutes or 30 cars per hour. If each 74-seat car carries 150 riders,
the maximum capacity is 4500 RPH, slightly more than 1/3 of promised capacity.
ST also anticipates
40,000 of the projected 50,000 daily East Link riders will come from
terminating all the cross-lake bus routes at either the South Bellevue or
Mercer Island light rail stations.
Thus, each morning and afternoon 20,000 transit riders will be required to
transfer to and from trains at the two stations. ST apparently doesn’t recognize the nearly 4½ hours required
for the 20,000 riders with its peak capacity 4500 RPH may not be acceptable for
many commuters.
Mercer
Island transit riders and those forced to transfer from buses there will have a
particularly difficult time since all the light rail cars will likely be full well
before they ever reach the station.
The lack of capacity and the hassle of transferring will undoubtedly
convince many to “drive” rather than “ride”.
Unfortunately
those choosing to drive will encounter the second “likely” reason for ST
delaying the 4th lanes; their concern about another DEIS claim,
namely:
“Travel
times across I-90 for vehicles and trucks would also improve or remain similar
with East Link”
ST assumes
the long-delayed added outer roadway lanes could make up for the loss of the
two center roadway lanes. They
were allowed to proceed with East Link because the WSDOT convinced a Kittitas judge
the added lane, their R-8A configuration, made up for closing the center
roadway. Yet the 2004 FHWA Record of Decision (ROD)
requires the “approved” R-8A configuration to maintain the two center roadway
lanes for vehicles. ST delayed the
4th lanes over concern any subsequent closure of the center roadway to verify
outer roadway capacity would fail.
Even worse,
outer roadway congestion will actually increase when East Link begins service
(2023?). First, as mentioned
earlier many transit commuters will chose to “drive rather than “ride”. Second, the lack of light rail capacity
will likely force ST to allow many of the cross-lake buses to continue on the
outer roadway into Seattle.
East Link will
also create a “financial black hole” for the entire area’s transportation
funding because of high light rail operating costs. The ST 2014 budget includes a $22.48 per car-mile operating
cost (excluding depreciation) or ~$90 per mile for their 4-car trains.
At that
rate the 26-mile Redmond-to-UW portion of the route will cost $4675 for each
round trip or $566,000 for the scheduled 121 daily trips. If weekend frequencies are half those
levels the operating cost will be $3.4 million weekly or $176 million annually. Depreciation will add $30 million to the costs assuming the
sixty ~$5 million cars required for East Link will last 10 years.
By
comparison, East Link fare box revenue will be miniscule. ST projects 40,000 of their anticipated
50,000 riders will transfer from buses to and from East Link at either Bellevue
or Mercer Island. Since those transferring presumably
won’t be required to pay twice, the only net fare-box revenue will be the
10,000 non-transfer riders paying ~$30,000 daily.
In essence
ST will be required to pay more than $500,000 daily to subsidize light rail
service that requires 20,000 bus riders to transfer to light rail at Mercer
Island or Bellevue rather than continue on the bus the remaining 6 or 8 miles into
Seattle. The fact that the East
Link trains won’t have the needed capacity adds to the insanity.
ST
exacerbates the East Link operating-cost problem with their decision to also route the trains to Lynnwood even though
the Central Link trains will have more than sufficient capacity. The 12.8-mile
Lynnwood extension will add 25.6 miles to the East Link route. ST schedules call for 484 cars daily
so the Lynnwood extensions will add 12,390 car-miles-per-day to East Link
operations. Again, if weekend car miles are half that level, East Link
will add 74,342 car miles per week or nearly 3.9 million car miles per
year.
At $22.48 cost per
car mile, the Lynnwood routes will cost an additional $87 million annually. Since Central Link trains provide
more than sufficient capacity for any potential riders, any East Link revenue
will be offset by a loss in Central Link fares. Even more absurd, the ST 2040 plan to extend light rail the
~10 miles to Everett will nearly double the annual operating deficit for the northern
route.
The bottom
line is East Link has been a transportation failure. 15 years ago ST could have moved non-transit HOV to 4th
lanes on the I-90 bridge outer roadways and initiated 2-way BRT service on the bridge
center roadway. The costs would
have been minimal and the additional riders attracted to direct bus routes into
Seattle would have reduced congestion throughout east side. Instead cross-lake commuters from both
sides of the lake have endured needless congestion for years while ST spent
hundreds of millions on consultants for detailed designs and open houses for public
comment on things like light rail stations that won’t be needed until
2023.
ST past
failures will pale in comparison to the debacle that awaits the area if allowed
to continue. In 2017 they’ll close
the center roadway to begin light rail installation on the center roadway. If the 2004 FHWA analysis is correct,
outer roadway congestion will substantially increase. Over the next 6-7 years ST will complete construction of a
~$3 billion light rail system that will increase rather than decrease
cross-lake congestion, devastate parts of Bellevue and require an annual
subsidy of $285 million to cover operating costs.
ST’s goal
for doing all this is to increase the number of daily transit riders from 40,000
to 50,000. The fact that even this
meager improvement is “highly unlikely” surely qualifies East Link as a
debacle.
I’m here
today to ask the AWB for help in stopping it.
No comments:
Post a Comment