The January 11 Bellevue Reporter headlines “Sound Transit to start
probing along light rail line’’ is another example of ST incompetence. Any concerns they may have about
installing light rail tracks along the route into Bellevue pale in comparison
to those associated with light rail operation on the I-90 Bridge.
No one has ever attempted to install a train on a floating
bridge. The concern is with the
ability of the “expansion joints” connecting the “floating” and “fixed” portions
to withstand the loads from the train’s four 74-ton cars. (The original bridge
joints have already needed replacement under less severe loads.)
The Federal Highway
Administration (FHWA) was sufficiently concerned they responded to the Draft
Environmental Impact Statement on February 23, 2009 (HRW-WA/WA624). It concluded “We do not agree that enough work has been done to justify
that it is feasible to design an expansion joint to accommodate light rail”. (The “work” they
referred to was some 2005 tests the WSDOT had conducted using “flat-bed”
trucks. See 7/04/12 post for more details)
Chapter 7 of the Final Environmental Impact Statement (FEIS) does
mention these concerns: “The Federal Highway Administration’s (FHWA’s) concerns on the
Draft EIS focused on the feasibility of light rail on the floating bridge and
requested additional information on the feasibility of an expansion joint to
accommodate light rail.“
Table 7-1, Common Comments, includes the following question and ST’s
response
CC3n Can
the I-90 floating bridge structure support the light rail?
The Washington State Legislature Joint Transportation Committee
commissioned an independent review team (IRT) to evaluate the bridge design
with light rail. The IRT concluded that all issues identified as potentially
affecting feasibility can be addressed.
It’s “interesting” that ST chose to refer to a study commissioned
by the legislature rather than conduct further studies in the intervening 2 ½
years. The fact the independent
study concluded “all the issues identified can be addressed” surely suggests
more needs to be done.
As the 7/04 post points out future studies may conclude that structural
concerns could limit each train to only 2 cars; halving East Link’s already meager
capacity. The fact ST still
refuses to do those studies nearly 4 years after the FHWA raised concerns is
just another example of their incompetence.
No comments:
Post a Comment